A power study puts Anthropic-linked US sites mostly on fossil fuels, with major assumptions

The Better Data Center Project estimates that electricity serving a selected set of Anthropic-linked US data centers in 2028 would be about 87% gas and 11% coal. The figures are a modeled scenario, not measured consumption or an audit of Anthropic’s global power purchases.

Key facts

A cloud compute agreement is not the same thing as a power contract. Anthropic may buy access to servers operated by another company, which in turn buys electricity from a utility or develops generation. Those layers make the source of an AI system’s incremental power difficult to assign. The project attempts to reconstruct that chain for US sites it connects to Anthropic, rather than reporting meter readings.

For dedicated generation, its model uses emissions factors for on-site gas plants and new gas plants associated with data-center loads. For other grid-connected sites it uses the Environmental Protection Agency’s AVERT tool to estimate which existing generators respond to additional demand. That is a marginal question: imagine one more guest arrives at a restaurant and the kitchen fires up a gas burner to cook the extra meal. The extra burner’s fuel is different from the average energy used by the whole restaurant. Likewise, a marginal model need not match the average regional grid mix.

The model’s inventory is material to the result. Its 19 rows include planned and speculative projects, uncertain Anthropic shares at shared facilities and mixed construction statuses. Rated IT capacity is not average electricity use. The analysis assumes a 1.15 power usage effectiveness ratio and 70% utilization for its stated midpoint, and assumes all 9.6 gigawatts of identified high-case capacity is online in 2028. Those inputs are not established future operating facts. The article’s emissions range and the live workbook’s comparison range also differ; the reviewed record does not explain why.

There is primary evidence for pieces of the supply chain. Anthropic’s SpaceX announcement confirms a compute relationship, but does not specify the electricity mix. Amazon’s Project Rainier account says Anthropic uses that cluster. An Indiana utility order describes a pending agreement for two 1,300-megawatt gas facilities and a 400-megawatt battery intended to serve Amazon’s load. It does not assign a share of that power to Anthropic.

Anthropic’s infrastructure commitments say “much” of the new power it is working to add will be natural gas, while it explores other sources. That supports scrutiny of gas dependence, not the precise 87% estimate. Independent analyst WattTime argues that emissions depend on location and timing and that flexible demand can sometimes use otherwise-surplus renewable power. Its argument does not independently validate this project’s site inventory.

The workbook’s high-capacity case separates 2.510 gigawatts of on-site gas, 3.728 gigawatts at sites categorized as grid power with new gas, 3.172 gigawatts assigned to existing marginal gas and coal, and 169 megawatts assigned to nuclear. Those are categories of modeled IT capacity, not an itemized set of electricity purchase agreements. The model also includes a wide estimated Anthropic share at Colossus 2 and speculative attribution at some Amazon sites.

The distinction affects accountability. A compute customer may not own a generator, yet its demand can influence a supplier’s infrastructure plans. At the same time, assigning an entire shared facility to one customer without disclosed allocation can exaggerate that customer’s footprint. The workbook makes some such assumptions visible; readers should carry them alongside the headline rather than treat the inferred site list as a verified contract register.

The strongest objection to a headline reading is that future capacity, customer attribution and dispatch are all modeled. Short-run marginal analysis also does not predict every new plant or transmission upgrade that could exist in 2028. Conversely, using a regional annual average alone can conceal which generators respond to a new around-the-clock load. The useful conclusion is that siting, construction schedules and power procurement deserve the same scrutiny as chip contracts—not that a future global electricity bill has already been measured.


Primary source, verified: read the paper →

Key questions

Does 87% gas describe Anthropic’s measured electricity use?

No. It is the project’s model for selected US sites in 2028, with uncertain allocations and future construction.

Why use marginal electricity rather than the grid average?

The model asks which generation responds to added demand, a different question from the average fuel mix across an entire grid.
Cite this

APA

Ground Truth. (2026, November 22). A power study puts Anthropic-linked US sites mostly on fossil fuels, with major assumptions. Ground Truth. https://groundtruth.day/news/anthropic-linked-power-mix-is-a-model-not-a-meter.html

BibTeX

@misc{groundtruth:anthropic-linked-power-mix-is-a-model-not-a-meter,
  title  = {A power study puts Anthropic-linked US sites mostly on fossil fuels, with major assumptions},
  author = {{Ground Truth}},
  year   = {2026},
  month  = {nov},
  url    = {https://groundtruth.day/news/anthropic-linked-power-mix-is-a-model-not-a-meter.html}
}

Topics: energy · data-centers · anthropic · climate

Comments are replies to this story on Bluesky — reply with any Bluesky account to join in.